Activity durations and logic: the mechanical rules, agency by agency

These are the requirements a reviewer meets first, because they are the ones a schedule file answers on its own. A duration cap needs no correspondence to decide. A ban on start-to-finish relationships is a column in the relationship table. A rule against open ends is a count of predecessors and successors. None of them needs anyone's opinion about the work.

They are also where the sixteen public-agency documents read for this site disagree most concretely. Duration caps run from 15 to 30 days, in three different units. Two agencies permit exactly one relationship type; one permits three; one bans one; several say nothing. One agency prohibits constraints as a class; another requires two of them by name.

The comparison hub sets out each agency's whole requirement. This page follows the mechanics. For what the mechanics do — what a lag changes in a calculation, how a constraint interacts with a backward pass, the difference between total and free float — see lags and leads, schedule constraints and total float and free float. This page stays on what the documents demand.

Part one: duration limits

Read the unit as carefully as the number. Working days, workdays and calendar days are three different bases, and a 20-calendar-day cap is tighter than a 20-working-day one.

Agency Lower bound Upper bound Unit Clause
ADOT 1 day 15 working days §108.03
WisDOT 1 15 working days §108.4.4.3
NYSDOT 15, excepting submittal and procurement activities unless the Engineer permits otherwise work days Item 639 F.1(h)
WVDOH 15, except non-construction activities; longer ones kept to a minimum and subject to review working days §108.3.1.4
CDOT 15 days of work unless the Engineer approves; a series totalling five workdays or less may be grouped into one days of work 108.03(b)
PennDOT A 5-day fineness floor: detail is limited where possible to a minimum 5-day activity Activities over 15 are limited to a minimum working days 689.3(b)3
MnDOT (CPM) 5 20 working days §1803.3B.2
MnDOT (bar chart) 1 15 working days §1803.2B.1
Caltrans 1 20, unless otherwise authorized working days §8-1.02C(2)(10)
VDOT 20, unless the Engineer accepts otherwise work days II.2.A(6)(c)
TxDOT 20 unless agreed; each work activity also carries an estimated production rate per working day working days 5.2, 5.4
UFGS 01 32 01.00 10 Non-procurement original durations not to exceed 20 workdays or 30 calendar days both, in one sentence §3.3.2
NJDOT 1 workday 30 for construction activities, without the Resident Engineer's agreement days 153.03.01
SCDOT 30 original duration; an activity past 30 days of actual duration without further cost is ended and broken up calendar days Activities, Monthly Updates
MDOT SHA Submittal review activities no shorter than 30 days No cap. Anything over 10 work days is explained in the narrative each time it occurs work days §109.03.01.02(d), (e)
WSDOT No numeric cap. Durations are to be reasonable for the work and detailed enough that daily progress can be evaluated working days 1-08.3(2), items 3–5
Ohio DOT 20 without the Engineer's approval; maintenance of traffic, erosion control and similar items may not run as single activities to the Completion Date working days 108.03.A

Three of these are not caps at all, and the difference matters. MDOT SHA sets a narrative trigger at 10 work days: a long activity is permitted and has to be explained. WSDOT sets a standard — reasonable, and fine enough for daily evaluation — with no number attached. Ohio attaches the rule to a class of work rather than to a number of days, naming the items that most often become a single bar spanning the job.

And UFGS states two numbers in one sentence. §3.3.2 reads: "Non-procurement activities Original Durations (OD) are not to exceed 20 workdays or 30 calendar days." The reading that makes both operative is one limit selected by the activity's calendar — 30 where the calendar works all seven days, 20 otherwise. Reading it as both makes the second number unreachable; reading it as whichever is larger makes the first decorative. The clause does not say which.

ADOT attaches something no other agency does. §108.03 lets the Engineer call for the working behind any duration, naming four inputs: estimated manpower, equipment, unit quantities and production rates. A schedule file carries none of those, so the cap is checkable from the export and the justification is not. TxDOT's 5.4 comes closest by requiring an estimated production rate per working day on each work activity.

Part two: relationship and lag restrictions

Agency Relationship types permitted Leads and lags Clause
PennDOT Finish-to-start only. A single start and a single finish activity for the schedule; every other activity carries at least one predecessor and one successor Lag and lead incorporated as a separate activity. Redundant relationships not to exceed 5 percent of the total 689.3(b)3
WisDOT Finish-to-start only No leads and no lags §108.4.4.3
VDOT Finish-to-start, start-to-start and finish-to-finish, which excludes start-to-finish by omission Lag prohibited unless the Engineer permits it II.2.A(9)(a), (9)(e)
NJDOT Written from both ends: a start takes a start-to-start or finish-to-start predecessor; a completion takes a finish-to-start or finish-to-finish successor. Start-to-finish is not used Not restricted in the clauses read 153.03.01
CDOT Start-to-finish prohibited without the Engineer's approval Negative lags prohibited; lags over 10 workdays prohibited, both without approval 108.03(b)
NYSDOT Not restricted by type in the clauses read Lag may not exceed 10 days; negative lag prohibited Item 639 F.1(i)
UFGS Start-to-finish prohibited. Leads (negative lags) prohibited Lags must be reasonable as determined by the Government, and not used in place of realistic durations, to absorb or create float artificially, or to replace proper logic §3.3.16
MDOT SHA Finish-to-start generally guides the sequence; other types explained in the narrative Negative lag is not used §109.03.01.02(d)
SCDOT Not restricted by type in the clauses read Negative lag not used; lag minimised in favour of an activity standing for it Schedule Details
MnDOT Not restricted by type in the clauses read Lags and leads need the Engineer's agreement in advance and may be required to be replaced by an activity; the reason for each goes in the narrative §1803.3A.4, §1803.3C.1
TxDOT A predecessor and a successor for each activity Not restricted in the clauses read 5.3
ADOT The schedule shows the interrelationships among activities; no type restricted Not addressed §108.03
Caltrans Not restricted by type in the clauses read Not established
WSDOT Precedence diagramming method on Types B and C Not restricted in the clauses read 1-08.3(2)B
WVDOH Criterion 10 fixes one specific relationship: Notice to Proceed follows Project Award by a stated lag — 30 days ordinarily, 7 where the Contract carries an incentive/disincentive clause §108.3.2

Pennsylvania goes furthest in two directions at once. It permits one relationship type rather than prohibiting one, and it removes lag from the relationship entirely by making it an activity with a duration, an ID and a calendar. A ten-day lag is a number in the relationship table that a reviewer scrolling the activity list will never see; a ten-day activity named for what happens during those ten days is in the list, carries a calendar and can be progressed. MnDOT and SCDOT push the same way more softly — each prefers an activity to a lag without mandating it.

The five percent cap is the only ratio in this family of documents. 689.1 defines a redundant relationship as a link also represented by a parallel path, removable without affecting the logic or the calculations. Every other numeric rule on this page is absolute; a percentage of total relationships scales, so the same rule binds a 300-activity network and a 3,000-activity one at the same proportion. Its inputs are entirely inside the file.

Part three: constraints, open ends, and out-of-sequence progress

Agency Constraints Open ends Out-of-sequence progress
CDOT Prohibited as a class without the Engineer's approval Prohibited — and defined broadly: an activity whose only predecessor tie is start-to-start, or whose only successor tie is finish-to-finish, counts as open-ended Retained logic mandated where Primavera is used
UFGS Artificial float constraints such as zero free float or zero total float prohibited; mandatory constraints that ignore or affect network logic prohibited; no constrained dates beyond those the section specifies Exactly two permitted: the first activity has no predecessor, the last has no successor Permitted only case by case with the Contracting Officer's approval, with logic corrections proposed before the update and the condition addressed in the narrative
NJDOT Constraint dates only on Completion and interim completion milestones, which must exist as finish milestones carrying a late finish constraint Every activity except the project start and completion milestones carries predecessors and successors Not addressed in the clauses read
PennDOT Required in two places: Notice to Proceed takes a Start On or Start On or After; Project Completion takes a Finish On or Finish On or Before. Contract interim milestones take soft constraints and a seven-day no-holiday calendar Single start and single finish activity; everything else tied both ways Not addressed in the clauses read
VDOT Limited to milestones the Contract specifies. Start On, Finish On, Mandatory Start and Mandatory Finish prohibited outright The Make Open-Ended Activities Critical option must be unmarked Retained Logic required as a declared setting
WisDOT Limited to contractual constraints; the review guidance separately directs that the project Must Finish By constraint be removed Not restricted by a numeric rule in the clauses read Not addressed in the clauses read
MDOT SHA Used only where the Contract defines the restriction Every activity carries at least one predecessor and one successor, except milestones and the first and last activity Retained logic stated three times in the book; a condition unresolved 30 days after the activity started is corrected by formal revision
NYSDOT Any constraint the Engineer in Charge has not authorized in writing is a ground for immediate rejection An activity with no predecessor, or none with no successor, excepting the first and last, is a ground for immediate rejection Actual dates strictly after the data date are a ground for immediate rejection
MnDOT The reason and purpose of each constraint goes in the narrative At least one predecessor except the first, at least one successor except the last Not addressed in the clauses read
WSDOT Restraints permitted, but not so as to alter the network's logic or the critical path. On Type C, fixed constraints are identified on the activity listing with a written reason for each Not restricted by a numeric rule in the clauses read Not addressed in the clauses read
SCDOT An explanation of each constraint goes in the narrative A predecessor except the first, a successor except the last Retain logic required, progress override not permitted; out-of-sequence work and failed starts explained individually
TxDOT Not restricted in the clauses read A predecessor and a successor for each activity Not addressed in the clauses read
Caltrans Not restricted in the clauses read Not established Not established
ADOT Not addressed Not addressed Not addressed
WVDOH Criterion 15 of §108.3.2 governs which constraints are permitted Not restricted by a numeric rule in the clauses read §108.3.2 governs how progressed activities are recalculated

Colorado's open-end definition is the one that changes an answer. An activity whose only forward tie is finish-to-finish has nothing driving its finish through to what follows it, and an activity whose only backward tie is start-to-start has nothing driving its start from what precedes it. A check that counts relationships per activity passes both; a check written to CDOT's definition does not. The two produce different findings on the same file.

Two agencies contradict each other outright on one field. WisDOT's review guidance directs that the project Must Finish By constraint be removed; VDOT's Category III provision requires one, equal to the Contract Completion Date. Same setting, same file, opposite instructions. Nothing resolves that except the contract that governs the project. UFGS §3.3.8.2 takes a third position again, requiring the last activity to be a finish milestone constrained to the Contract Completion Date so that an early finish shows positive float and a late finish shows negative float on the longest path.

Network-shape rules: counts and proportions

Four documents state a rule about the network as a whole rather than about any one activity, and these need the population counted rather than a row read.

Agency Rule Clause
Caltrans At least 50 and not more than 500 activities, unless otherwise authorized. Not more than 50 percent of baseline activities critical or near critical — with near critical defined as total float above the critical path's but not more than 10 working days §8-1.02C(2)(5), (6); §1-1.07B
MnDOT Not more than 20 percent of activities critical, and not more than 30 percent near-critical, unless otherwise authorised §1803.3B.2
WVDOH At least ten activities per million dollars of Contract, and not more than three hundred §108.3.1.4
PennDOT Redundant relationships not to exceed 5 percent of the total number of relationships 689.3(b)3
CDOT Near critical defined as total float of five days or fewer, or as the Engineer defines 108.03(a)

Note that Caltrans and CDOT define the near-critical band at different widths — 10 working days against 5 days — and MnDOT states a cap without printing a band in the clause read. A near-critical share is not comparable between agencies unless the band is stated with it.

What this project does with these clauses

Almost everything on this page is decidable from an imported file: durations and their units, relationship types, lag values and signs, predecessor and successor sets per activity, constraint types and dates, calendar assignment, activity counts, and the float that follows from the network. This project computes and reports them and cites the clause — see what the engine does, how it works and reading a report.

Four things it does not do.

Which of these clauses governs a particular project is a fact about its incorporated contract documents — the edition named, the special provisions, and for several agencies the schedule type or tier the procurement selects.

Source: web/pages/activity-durations-and-logic.md. Source commit date: 2026-09-11.