NYSDOT CPM scheduling requirements: Item 639 Type 2

The New York State Department of Transportation states its critical path method requirement as a special specification item incorporated into the contract: Item 639.2X010011, "CPM (Critical Path Method) Progress Schedule — Type 2", dated 15 August 2014, 30 pages. Because it is an item of the contract, it outranks any general standard it conflicts with on a project that carries it.

A second NYSDOT document sits beside it: the agency's Best Practices for CPM Schedule Specification Compliance manual, 9 May 2016. It restates Item 639's rejection criteria and names, for each, the numbered P6 filter a reviewer applies — then lists all twenty-nine filters. It says of itself that it is guidance and not official policy, and that it does not replace the Item 639 specification. That distinction is load-bearing here: guidance does not breach. Where only the manual states a predicate, this project reports an observation rather than a failure, and says which document it rested on.

Section numbers, thresholds and filter identifiers below are stated in this project's own words with the citation attached. The manual asserts no copyright notice, which is a finding and not a permission; a New York State agency document is not a federal work.

What Item 639 requires

Requirement What Item 639 Type 2 states Clause
Scheduling software Oracle-Primavera P6, named — and hosted on the Department's own servers, with contractors working in NYSDOT's environment through Department-issued accounts. Item 639, software provisions
Baseline schedule Due at award. Beyond mobilisation, procurement and erosion control, work may not start until the baseline has been submitted and is free of the paragraph I.1 immediate-rejection deficiencies. The Engineer comments on an optional draft baseline within 5 Work Days. Item 639 paragraph I.1 and the baseline provisions
Update frequency Monthly progress schedules, plus a weekly status report. Item 639
Narrative Required. Item 639
Recovery schedule A defined term in this specification, unlike several of the other agencies on this site. Item 639
Time impact analysis A defined term in this specification. Item 639
Float ownership Total float is defined as an attribute of a network path, not of an individual activity. Item 639 expressly names float suppression — zero-free-float constraints, padded durations, over-restrictive calendars — as preventing true sharing of total float between the Department and the Contractor. Item 639
Activity durations Not more than 15 work days, excepting submittal and procurement activities, unless the Engineer permits otherwise. Item 639 F.1(h)
Lags Lag may not exceed 10 days, and negative lag is prohibited. Item 639 F.1(i)
Milestone calendar Milestone activities take the standard Global calendar the clause names in full — a 365 day / 8 hour Milestone/Curing calendar. Item 639 F.1(g)

Nine deficiencies that end the review before it starts

Paragraph I.1 lists nine deficiencies that are grounds for immediate rejection by the Engineer in Charge, without further review, analysis or comment. Four of them are decidable from the schedule file alone:

Three more are facts about the submission rather than the schedule: failure to schedule as of the data date, failure to attach the Scheduling/Leveling Report, and failure to attach the narrative and appendices. A schedule file records none of them, and this project does not report on them.

The Department-hosted P6 environment

Of the five agencies described on this site, NYSDOT's software requirement is the strongest. Other agencies name P6 and a file format. NYSDOT names Oracle- Primavera P6 and hosts it: the schedules live on Department servers and the Contractor works there under an account the Department issues. That changes what "submission" means — the schedule is not only delivered to the agency, it is built inside the agency's environment — and it explains why the Best Practices manual is organised around global P6 filters a reviewer runs against that database rather than around documents a reviewer receives.

Float suppression, named as such

Most specifications on this site say float is shared and stop there. Item 639 goes further and names the mechanisms by which a schedule can appear to share float while not doing so: constraints that drive free float to zero, durations padded beyond the work they represent, and calendars restrictive enough to absorb time that would otherwise show as float. The clause's stated purpose is true sharing of total float between the Department and the Contractor.

Two of those three mechanisms leave marks a file carries — constraints and calendars — and the third, padding, does not, because a duration does not record what it was intended to absorb. This project reports what the imported schedule contains and cites the clause; it does not conclude that any particular duration was padded.

Where Item 639 differs from the manual, and it is not cosmetic

What this page does not tell you