WVDOH CPM scheduling requirements: Standard Specifications §108.3

The West Virginia Division of Highways states its critical path method requirement in the body of its own Standard Specifications for Roads and Bridges, 2023 Edition (adopted 16 December 2022), at §108.3, "Prosecution of the Work" — not in a special provision. Because it sits in the book every contract incorporates, there is no tier to classify and no bid item to look for.

The supplements were read and neither revises this section. The 2024 and the 2025 Supplemental Specifications were both searched: neither carries a Division 100 entry for §108, and the only occurrence of "108" in either is a cross-reference to a different subsection. So the 2023 text is the operative text, and this page cites it without a supplement qualifier. That is a measurement rather than an assumption, and it is the first thing an agency reviewer will check.

What §108.3 requires

Requirement What the 2023 Edition states Clause
Scheduling software Primavera Project Manager P6, version 6.0 or higher — named, with a version floor. Submission in .XER format, plus a hard copy. §108.3.1.4
Preliminary schedule Within 30 calendar days. §108.3.1.2
Detailed schedule Within 60 calendar days. The Engineer reviews within 14 calendar days. §108.3.1.3
Official schedule Must be completed within 90 calendar days of Contract award. Payment is withheld after 90 days until the Schedule has been reviewed. §108.3.1
Update frequency Monthly, within 5 working days after month end, with monthly Project Control meetings. §108.3.4
Narrative Required with each monthly update: progress along the critical path in days ahead of or behind, impacts, and corrective actions. §108.3.4
Revised schedule trigger A delay greater than 10 calendar days on any critical activity, among other conditions. The revised Schedule is due within 7 calendar days of the Engineer's written request. §108.3.5
Time impact analysis Not named in §108.3. Time extensions route to §108.6. §108.6
Float ownership Positive float is shared, with neither side holding it exclusively; each has full use of what remains. §108.3
Activity durations No activity over 15 working days, except non-construction activities. Longer ones are to be kept to a minimum and are subject to the Engineer's review. §108.3.1.4
Activity count Bounded on both sides: at least ten activities per million dollars of Contract, and not more than three hundred. §108.3.1.4

The 90-day payment gate

Most scheduling specifications attach no consequence to a late schedule beyond the general remedies of the contract. §108.3.1 attaches one directly: the official Schedule must be completed within 90 calendar days of Contract award, and after 90 days payment is withheld until the Schedule has been reviewed.

Read with the three clocks above it, the section describes a staircase rather than a single deadline — a preliminary schedule at 30 calendar days, a detailed one at 60, the Engineer's review running 14 calendar days from receipt, and the whole sequence landing inside 90.

None of those dates is recorded in a schedule file. A schedule carries a data date; it does not carry the date it was submitted or the date of Contract award. This project treats every one of these deadlines as a fact about the submission rather than about the schedule, which means it does not check them, and its silence about them is not a statement that they were met.

Fifteen numbered criteria, and the one nothing else could decide

§108.3.2 states fifteen numbered criteria governing how the schedule is built in P6. Six of them are properties of the exported file: which calendars may exist and how they must be named, which activity must come first, which must come second and with what lag, how progressed activities are recalculated, and which constraints are permitted.

Two are worth describing in full.

Several criteria are stated and not decided here, and the reason is the same one each time: the field is not carried in this engine's schedule model. The Project Resource Tree and Cost Accounts Tree, Project Codes, and Global Activity Codes all fall there. A check over an absent field passes every schedule, which is the least useful result available.

A second document, and a real problem with it

WVDOH also publishes a Construction CPM Schedule Review Manual — 342 pages of Primavera P6 training material written for the Division's Construction Engineers and Area Engineers, built around two schedule review checklists it publishes in full and then walks item by item. It is not a term of the contract, by its own opening words, so where this project reports against it, it reports an observation and never a failure.

Its specification cross-references do not all resolve against the 2023 Edition, and that is a finding worth stating. Three were checked. One cites a subsection that is correct today. One cites a clause number for the Preliminary Construction Schedule that belongs to Extension of Contract Time in the 2023 book; the preliminary schedule is elsewhere. One cites a section number that in the 2023 book is Field Office and Storage Building. The manual is written against an earlier edition.

The consequence for anyone using it: read the specification citations out of the 2023 book directly, and treat the manual's checklist item labels as the stable identifiers, because those are the manual's own and cannot go stale against a specification revision. That is what this project does — its specification rules cite the 2023 book, and its manual rules cite checklist items.

Also worth knowing: WVDOH's separate Construction Manual directs the Project Engineer or Supervisor to review each schedule against the specification within fourteen calendar days, and refers that person to internal training documents for schedules.

What this page does not tell you