Source validation

Project
GENERATED-CLAIM-DEMO
Date prepared
2026-09-10
Engine
0.3.0
Input digest
sha256:f0fa6e8fc1fcd10460f591b01ca97b126cb84d37dccd2d841d3d81cbf5edd161

Date prepared is a self-asserted local time, read from the clock of the machine that ran this analysis and checked against nothing. It records when this document was produced. It is not evidence that this document, or the files it describes, predate any dispute; only an external timestamp authority is, and this engine wires none up.

Reservation of determination

Whether this submission is acceptable is the determination of the reviewing authority. This report states what the schedule imported from the supplied material contains and what the cited clauses say. It is not an engineering opinion and does not certify, approve or reject anything.

Method

No method has been declared for this analysis. Under AACE RP 29R-03 the method is itself an argument to be made and defended, so this report cannot be presented as a delay analysis until one is stated.

Governing documents

No governing document was established for this project. The analysis proceeds under AACE RP 29R-03, which is an assumption of this report and not a fact about the contract. If another document governs, conclusions resting on the choices disclosed below may change.

  1. AACE RP 29R-03
  2. ANSI/ASCE/CI 67-17
  3. SCL Delay and Disruption Protocol, 2nd ed.

Where the governing documents disagree

which standard governs the analysis on US federal work

concurrent delay: which of two overlapping delays is the cause

Choices that could have gone the other way

The following choices were made and their effect on this schedule was not measured. Establishing that would mean rescheduling the file under each alternative, which is a separate exercise. They are listed so a reader knows the choice was made, not so a reader can assume it did not matter.

Assumptions

AACE RP 29R-03 governs this analysis

Limitations

Findings

Each finding below names a clause of a cited document and states what could be established about it: that the condition the clause states is met, that it is not met, that a condition is stated but not scored, that the evidence is assembled and a person must decide, or that an input the clause turns on was not supplied. Whether the submission is acceptable is the determination of the reviewing authority, in the terms reserved above; a finding that a stated condition is not met is not a determination that the submission is rejected.

The weakest step in the reasoning below is computed_unvalidated. No conclusion drawn from it is stronger than that.

Schedules considered

computed

Every file supplied was read, including any the chosen method does not consume (AACE RP 29R-03 §1.5.B principle 7). Not all of it was read exactly as written. The counts above describe what was imported, which is what every finding in this report is computed over. What the importer could not take literally, and what it did instead:

Source validation

computed_unvalidated

9 passed, 2 failed of 21 source validation checks. This is not scored, and deliberately: one failure can make every number computed from the schedule unusable, so a rate would average away the finding that matters.

Failures (2)

Observations — worth a look, not a breach (3)

Referred — the evidence is assembled and a person must decide (3)

Not evaluated — one input away from deciding (4)

Run unanswered on the same file to read this list by input rather than by clause. It groups these entries by the thing a person would go and supply, and counts the clauses each one would make decidable — decidable, not passed, because a clause that runs can still fail.